Brownstone Restoration – Work Resumes


After almost 3 months of pause due to Covid-19 restrictions, the masons came back to work on June 8th. With Phase 1 reopening, non-essential construction was finally allowed to resume in New York City. We had been living behind scaffolding and plastic sheets covering the windows this whole time, so we were very happy to have the work start up again.

Prior to the work stoppage, the masons had applied the scratch coat to the top floor and were halfway done with the parlor level. On Monday, the they picked up where they left off in March and are now working on the parlor level and basement level scratch coat.

The masons estimate that they have about 2 and a half weeks worth of work left on the scratch coat. After that, they will leave for about one month while the scratch coat cures.